Tuesday, November 14, 2006

chillin' at school "K"

This is school "K" the before picture, the veiw is from the back, my station here is set on the southeast corner... in the swamp! someone needs to extend the building pad a little more.


Kenny was here a couple of days ago, stocking material and painting 90's. There is a skeleton crew over at "I" still working on the perimiter Lighting run







One day later were diging like angry moles, at this rate we'll be done before anyone knows we were here.

Tuesday, October 31, 2006

Tilt wall majic



Waiting on the crane... Now you dont see it....




They actualy finished after I left yesterday. The first 2 day set i've ever seen, Amazing

Monday, October 30, 2006

The ultimate ladder safety methods are being perfected here.

Al is wiring a box that will be 26 feet from the ground when the wall is up, but for now... no ladder needed!








with todays layout methods we don't have to wait for walls to be finished to do our work
















Ready to go!

Thursday, October 26, 2006

Tilt wall rough in...walls are being formed on the newly poured slab. Like giant 50,000 pound puzzle pieces, in a few weeks these will make a building Take me to your leader... this is not an alien timecapsule. Bearing the number of it's destination panel this premade ready mount product saves a considerable amount of time, and way less panic than the "old days" of tilt wall rough in.


Tuesday, October 24, 2006

Advancing the frontier of the internet


Pushing the envelope of the web deep into Osceola County.
Someday soon productive schoolchildren will develop their own blogs here

One week Later

The "before" picture. Surveyor putting in the corner points.












Begining of the Main Electric room. 1st ones to hit the slab!

August 15


August 15th arival on site, picking a spot for "camp". Picking a spot for the temp electric service.